·Urban Infrastructure Construction

No

Project Name

Construction Scale and Content

Total In’t(USD 10000)

Project Progress

Projector Initiator

Liaison

Telephone

No.1
319 National Highway Ningxiang County Section (Chuwei Road) Weatern section reconstruction project
319 National Highway Ningxiang County Section (Chuwei Road) Weatern section, it is intended to broaden the width to 30 meters,dual four-lane carriageway,seperated by green belt in middle, the symbol engineering is built in both ends. 
3000
The eastern and middle section has been reconstructed, and western section has been approved for feasibility study. 
Ningxiang County  Investment & Cooperation Bureau 
Peng Zhiyong 
0731-8980178
13874890159
No.2
Changsha Binjiang Avenue T-shaped section construction 
Changsha Binjiang Avenue T-shaped section is the main road along eastern of the Xiang River, it is Changsha Xingang Town Xianinggang old market Town in the south,and is T-shaped Town Tongguanyao in the north, via  six villages, as T-shaped Town Fanshenyuan Village, Jinyun Village, Xingcheng Community, Shutang Village, Shishe Lake and Caitao Village, the total length is 20 kilometers. The design of the road is dual four-lane with 36 meters in width.
1600
The plan & design has been completed.  
Wangcheng County  Investment & Cooperation Bureau 
Liu Changfu
13007490499
No.3
Wangcheng County T-shaped Industry Park Avenue construction 
T-shaped Industry Park Avenue is two trunk roads of  T-shaped Industry Park Avenue in length and breadth, ie., western connection of park road, southern connection of park road with the total length is about 5.8 kilometers. The road is designed as dual four-lane with 36 meters in width.
700
The plan & design has been completed.  
Wangcheng County  Investment & Cooperation Bureau 
Liu Changfu
13007490499
No.4
Wangcheng County Yinshan Road 
Yinshan road construction is one of the trunk roads in Wangcheng County Xingcheng district road network. The road starts from the junction of Yinxing Eastern Road & Jinxing Avenue, ends at Xiang River Shanchaji Bridge in Yuelu District. The whole road runs trough Xingcheng Town Yinxing Village with total length about 5.6 kilometers. the road coverage is 434mu. It is designed according to urban main trunk road with dual six-lane and 46 meters in width.
4137
The Yinshan Road has been finished listed as project and construction design. The levy and remove work has being undergone, the road red line has been prlonged to Provincial Land and Resources Office.
Wangcheng County  Investment & Cooperation Bureau 
Liu Changfu
13007490499
No.5
Wangcheng County life garbage transfer station 
The initial selected site is Huangjin Village Fengshu Po with land coverage of  45 mu and total construction area 16,070  square meters. the daily garbage treatment is 500 ton. The service area is covering the county western Xiangjiang River bank area, mainly for county and Gaoxing group, as well as villages and towns as Leifeng,Wushan, Dazongyuan etc. It is  large size(Ⅱ) life garbage transfer station to transfer garbage to urban solid castoff fill site for treatment. The main constructions are comprehensive biulding, compressing workshop, machinery repair workshop, power distribution room, door guard, measure pound room,canteen,terrace,  vehicle lane, as well as the subsidiary facility construction, such as water, electricity, road, car park, greening etc. 
550
The project has been finished previous preparation work, such as feasibility study, enviroment comprehensive appraisal, initial site selection plan land declaration. The project has been approved by County Government Standing Committee Conference, the construction period is one year.
Wangcheng County  Investment & Cooperation Bureau 
Lin Bo
13808432589
No.6
Changsha Chemical Industry Base infrustracture construction 
In order to improve Changsha-Zhuzhou-Xiangtan environment condition and quicken the development of small cities& towns and inductrialization process, as well as graspp the opportunity of Huadian Changsha  Electric Power Plant in Tongguan Town, It is intended to construct Changsha Chemical Industry Base in Northeast corner of Tongguan Town and northern of Changsha Electric Power Plant. This project is divided into three stages, the first stage covers 4,500 mu,and is mainly for infrastructure adn subsidairy construction, such as land leveling& road, water supply and drainage, power supply, communication, heat power, network, greening, flood prevention, as well as outter traffice trunk road, sewage treatment factory and industry usage water factory. 
15900
It has been completed the whole design, land untilization whole plan, previous landoform mapping plot, environment appraisal outline and feasibility study, the prolonged Power factory avenue of the main trunk road of the base has been  finished road bed. 
Wangcheng County  Investment & Cooperation Bureau 
Liu Changfu
13007490499
No.7
Liuyang River Middle Road project 
Liuyang River Middle Road  locates at Huaichuan Street affair office and Guankou Street Affair Office, from Liuda Road in the West and end at Jingcheng Avenue in the East, with Liuyang River in the South, and reaches Cuiyuan Road and Shuijia Road in North.  The project is the key junction of Liuyang new and old city zone, is the golden yard of tne new city zone.  The land is in L-size, it is 320m-530 m from south to the north, 3,300 meters  from east to the west, the total land coverage is  1,579 mu. According to Liuyang whole layout and controlling detailed plan requirements of this city, the land is comprehensive lan , which can be used as commercial, residence, finance, recreation etc.
46478
It has been listed into the urban whole layout. 
Liuyang Urban Construction Group Co., Ltd 
Ling Jianzhou 
0731-3655108
No.8
Changsha water diversing & water quality environment engineering Liuyang City water supply project
It connects main pipe water diversion gap of Changsha diversion engineering, divert the water to Liuyang urban zone. The main pipe is 5,000 meters with subsidairy pipe lines 12,000 meters and other subsidiary facilities. 
736
Continued construction 
Liuyang Tap Water Company 
Jiang Heping 
0731-3611492
No.9
One river, two banks, three districts development 
It is to construct Ningxiang RBD Core district, Ningxiang ecological sustainable development community, Ningixiang golden commercial zone, Ningxiang core scenic spot area. The planned area is 56773 mu,man power wetland is 3,000mu,newly added planned land is 21,370 mu.
10000
It has been listed as project, the dismantling work has been completed, three districts removal started. 
Ningxiang County  Urban Construction Investment Co., Ltd 
Lu Haoming 
0731-8980036?? 13975868227
No.10
The second stage of Ningxiang County Yuening Road construction  
the first stage of Yuening Road prolonged in the south, starts from Renmin south road, and connect the Wei River bank and natural scenic view along the river project. 
3000
The first stage work has been completed, and the second stage completed the design. 
Ningxiang County  Investment & Cooperation Bureau 
Chen Yonggao 
0731-8980178 13308437999
No.11
Ningxiang County Renmin North Road link construction 
It starts from Labour Cultural Palace of Renmin North Road , linking with Xin Renmin Road North Road and the yihuan Road juncture. The total length is 1.196 kilometers,it is the main traffice road of the county road network as three road from east to west & four roads from south to north. 
556
The project has been finished plan. 
Ningxiang County  Investment & Cooperation Bureau 
Chen Yonggao 
0731-8980178 13308437999
No.12
Ningxiang County Urban Sewage Treatment factory 
The project has been divided into three stages, It is 5000 cubic meters per day in every stage.
2200
The project has been listed for project.  
Ningxiang County  Investment & Cooperation Bureau 
Ou Zhaobo
0731-8980036
13875869678

 

Home  ︱ E-mail
Address: 10th Floor, Municipal Government Mansion, No.218, Yuelu Road, Changsha, Hunan, China

For Commercial Service :+86 731 8668012 For Investment Consultation:+86 731 8665557 Fax:+86 731 8666068

For further information,please log onto:www.cstrade.gov.cn